BACK Sinosteel MECC Contracted Indonesia Lampung coal-fired power projects put into operation
RELEASE TIME:2013-10-30 SHARE:

Recently, Sinosteel MECC undertake Lampung 2x7MW coal-fired power project in Indonesia had completed 72 +24 hours of continuous commissioning tests,which marking the successful completion of the project.

In April 2011, Steel MECC signed 2x7MW SDP coal-fired power project EPC contract with Indonesia Lampung , scope of the contract includes the provision of two generators boiler, turbine and supporting ESP, of the water, lose coal, ash handling system, Sinosteel MECC undertake design, equipment supply, installation, commissioning and commissioning. Contract in September 2011 came into effect.。

The project is the first Sinosteel MECC EPC coal-fired power project in Indonesia.The successfully completed of the project,which drive the company will further develop Indonesia and other Southeast Asian countries the market has laid a good foundation for power generation projects.