PROJECT NEWS

BACK Hot Commissioning Achieved Successfully for CCM Project for TOSYALI, Turkey
RELEASE TIME:2009-11-18 SHARE:


On November, 13th, 2009, the hot commission of 1.1mtpa slab caster project and rough rolling part of continuous hot rolling project, which is contracted by Sinosteel MECC, was successfully achieved in one time, marking the largest CCM and HSM project built by Chinese companies in overseas market entered into hot commission stage. High appreciation was extend to Sinosteel MECC from TOSYALI steel plant.

The contract of TOSYALI 1.1MPTA CCM and HSM project was signed and started in January, 2008, with contract value of approx 150 million US dollar. Sinosteel MECC’s scope covers design & engineering, equipment supply, erection and commission.

This project is listed one of four key projects of Sinosteel MECC and is paid much attention. Sinosteel MECC staffs along with workers of the owner have been working hard together. Leaders of Sinosteel MECC have made continuously communication with the client, efficiently get through the difficulty during project executive and the impact of the global financial crisis.

At present, engineering and project management staff from Sinosteel MECC are working hard on site, ensuring overall put into production of this project before December. 20th.