At 16:28 on March 20, 2010, the 2# coke oven on-load test run is successful for the enterprise undertaken by the company and coke is smoothly extracted. Since drying in December 2009 in this project, the company overcomes difficulties as low temperature, raining and snowing and difficult organization of construction personnel during spring festival, and with delicate organization, smooth startup of the project is realized which again demonstrates the technical level and project organization and management capability of the company in construction of large coking project.
Currently the company is organizing engineering technical and site management personnel for the assistance in the startup of 2# coke oven for creating conditions for the complete startup of the following 3# and 4# coke ovens.