At 16:58, on Nov.26th, 2009, hot commission of Cangzhou I&S Complex Phase II, 150t converter steel making project, achieved success in one time and officially put into operation.
This 2# 150t converter project was commenced in May, 2009. Sinosteel MECC has making great effort to deal with the affect of world economic crises and all the difficulties since the ground breaking. It takes only 6 months from the ground breaking to the project construction and hot commission implementation, fully expressed Sinosteel MECC’s capacity to undertake the construction of large scale integrated steel plant.
Presently, Sinosteel MECC’s work team for this project has been working hard to pay the way for allround production of Phase II project.