Duration:2011 - 2014
Project overview:
The BIGA 2x600MW Power Plant of ICDAS, situated on the south bank of Marmara Sea, is 30 kilometers from Biga City. The plant was designed to construct 2x600MW supercritical condensing coal-fired units and Sinosteel has delivered the second 600MW generating unit with its auxiliary facilities in the reserved expanding area.
Scope of supply:
design, equipment and material supply, technical supervision and commissioning.