On July 20, 2010, successful on-load test run of 1# 360 m2 sintering machine technical modification project of Liuzhou Steel undertaken by SINOSTEEL Equipment and Engineering Co., Ltd. in form of PC contracting is realized.
The 1# 360 m2 sintering machine technical modification project of Liuzhou Steel is the second 360 m2 sinter production line undertaken by SINOSTEEL Equipment and Engineering Co., Ltd. in Liuzhou Steel. With delicate organization, scientific management, intensified communication and cooperation with the owner, design institute, equipment manufacturer and construction company, all works for the project from civil work construction, equipment supply and installation and commissioning are completed only with 7 months, which completely stands for the technical power and advantage of project organization and management of SINOSTEEL Equipment and Engineering Co., Ltd. and it is highly praised by the owner and the friendly cooperation existing between the company and Liuzhou Steel is further strengthened.
Currently the project management and engineering technical personnel of the company are endeavoring for the final acceptance test of the project.