At 15 clock on June 29, 2010, the 110 t/h coke dry quenching project of Liuzhou Steel undertaken by SINOSTEEL Equipment and Engineering Co., Ltd. in form of general contracting is smoothly started up which is the third coke quenching dry project smoothly contracted and constructed by the company in Liuzhou Steel.
The project is important project for energy saving and emission reduction, since commencement in August 2009, the project department of the company in this project delicately organized and strictly managed to overcome adverse factors as narrow construction site and storm in south of China, and smooth startup is realized only with a period less than 11 months which is 3 months earlier than scheduled in the contract, and it is highly praised by the owner.
The earlier construction and smooth startup of the 110 t/h coke dry quenching project of Liuzhou Steel again demonstrates the technical power and service level of SINOSTEEL Equipment and Engineering Co., LTd. in construction of coke dry quenching project and it further deepens the perfect cooperation between the company and Liuzhou Steel, establishes perfect credibility of SINOSTEEL, and it creates perfect conditions for the development of the company’s technological and project management advantages and further development of coke dry quenching project market in foreign countries.
Currently the equipment operation of the project is perfect and it has entered stable trial production stage. All personnel revolved in the project are endeavoring to cooperate with the Liuzhou Steel for production target and for the final acceptance test.