19
2023-07
Indonesia is the birthplace of the "Maritime Silk Road." On July 19, 2023, the first coke oven of the Risun Weishan 4.8 million tons/year coking project, undertaken by Sinost...
18
2023-07
"The 2.5 million-ton coking project is a crucial initiative for MMK's upgrade, aimed at increasing coke production efficiency and improving the ecological environment. Currently,...
19
2023-06
Guided by the goal of becoming a leading enterprise in low-carbon metallurgical technology in China, Sinosteel Equipment & Engineering Co., Ltd. (Sinosteel MECC) has ma...
24
2007-12
SINOSTEEL MECC contracted No.1 and No.2 Coke Oven Project for Xinjiang Bayi Iron & Steel Plant of Baogang Group. In the wake of putting No.1 coke oven into production on 23rd November, Sinosteel MECC put No.2 coke oven into production on 16th December, 2007, after heating up of 3 months. B...
24
2007-12
On November 15th, Turkey ISDEMIR officially signed on the certificate of business operation of PCI Sinosteel MECC contracted for its No.1 (1300 m3), No.2 (1300m3) and No.3 (2000m3) blast furnaces. And the PCI project has been officially put into business operation to date. The contract for ...
20
2007-12
On Dec 15th, 2007, SINOSTEEL MECC successfully won the contract to supply T Group with complete set of continuous slab casting line, strip hot rolling line, oxygen plant and water treatment plant for whole factory after over one year effort. SINOSTEEL MECC was in receipt of the down payment on...
05
2007-12
On Nov 30th, SINOSTEEL MECC successfully put the No.5 Coke Oven of ISDEMIR (Turkey) into production after heating-up for 3 months. In June and July of 2004, SINOSTEEL MECC signed contract with ISDEMIR to supply with No.5 and No.6 Coke Ovens and related coke oven machines. Under the contract...
07
2007-11
SISCOL 400,000t/a Non-recovery Coke Oven, contracted by SINOSTEEL MECC, was successfully put into production with 6 months of hard work by SINOSTEEL Staffers, in the wake of successful output of quality coke with former 48 chambers on Feb 16th 2007. The present 48 chambers of the coke oven was...